Construction Schedule...anticipated, as of April 16, 2015
April 21 to 22 Clearing of brush along trail by contractor
April 23 to 24 Installation of erosion controls
April 27 to May 12 Removal of iron rails
May 13 to May 29 Removal of wooden ties
Some form of barrier will be installed just prior to reaching the Charles River, and just prior to reaching the High Rock bridge to show the ending points of the 1.7 mile pedestrian path. The surface will be back-bladed for informal use until the Town is able to complete the procurement process for the next stage of construction, which will include a stone dust surface, safety fencing, and improvements at the road crossings.