Project Update for the week of December 3 - December 7, 2018
Last Updated: 12/4/18

  • Conference call held with vendors on 11/29/18
  • Graybar (vendor supplying LED fixtures) provided a status update on when remaining fixtures will ship:
    • 600 fixtures anticipated to ship 12/14/18.
    • 1180 fixtures anticipated to ship towards the end of December.
    • Fixtures will be shipped directly to Dagle Electric (Installer) and pre-fabricated before being delivered to Needham.