Help Center
Go To Search
Click to Home
Construction Alerts
Construction Alert Banner

Anticipated schedule for August 13 - August 17, 2018


Construction schedules are weather permitting and are subject to change.

Thank you for your cooperation!

Last updated: 8/16/18

Central Ave at Cedar Street
The Town's contractor is completing punch-list items. Pavement markings will be restored in the next few weeks. The Town will announce the anticipated date once we receive notification from the contractor. Expect minor delays. 

Oak Street & Marked Tree Road Water Main Improvements
Crews will continue to install new water main pipe on Oak Street. Oak Street (from Maple Street to Marked Tree Road) will be closed to through traffic from 7:00 AM - 4:00 PM. In addition, some side streets located off Oak Street will be temporarily closed to through traffic for short periods of time. Please seek an alternate route. For information about upcoming water shut-off's, please scroll to the bottom of this page. 

Greendale Ave (from Rosalie Road to Cimino Road)
The Town's contractor will continue to mill the roadway and raise castings in and preparation for final paving. There will be no on-street parking Monday-Friday from 7:00 Am to 5:00 PM. Expect delays. 

Edwardel Road, Savoy Road, Wyoming Ave (from Arden Street to Hillcrest Road), Arden Street, Woodledge Road & Fletcher Road
Final paving is complete. The Highway Division will continue to work on punch-list items including, driveway apron adjustments, loam and seeding grass areas. Expect minor delays.  

Brookline Street (entire length)
Due to weather delays, the rubber chip seal surface treatment is now scheduled to be applied the week of August 27, 2018. Please seek an alternate route, temporary road closures will be in effect and traffic will be detoured. 

Forest Street (entire length)
Due to weather delays, the rubber chip seal surface treatment is now scheduled to be applied the week of August 27, 2018. Please seek an alternate route, temporary road closures will be in effect and traffic will be detoured. 

Nehoiden Street (entire length)
Due to weather delays, the rubber chip seal surface treatment is now scheduled to be applied the week of August 27, 2018. Please seek an alternate route, temporary road closures will be in effect and traffic will be detoured. 

Webster Street (from Central Ave to Highland Ave)

Due to weather delays, the rubber chip seal surface treatment is now scheduled to be applied the week of August 27, 2018. Please seek an alternate route, temporary road closures will be in effect and traffic will be detoured. 

Oakland Ave
Sidewalk rehabilitation work will begin this week. A Town hired contractor will remove existing sidewalks, install granite curbing and handicap ramps at intersecting streets. Driveway aprons will be adjusted as needed and grass areas affected by the construction will be loamed and seeded. Expect minor delays. 

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Oak Street & Marked Tree Road Water Main Improvements 
Water Shut-off & Construction Notifications

Residents on Oak Street are currently connected to the water by-pass.This by-pass enables residents to have access to water at all times throughout construction. 

IF YOU ARE EXPERIENCING ANY ISSUES WITH THE TEMPORARY WATER SERVICE, PLEASE CALL REVOLI’S 24/7 RESPONSE LINE FOR ASSISTANCE
(978) 815-7825. 


Shut-off scheduled for Friday, August 17, 2018 at 9:00 AM
**If the contractor is unable to perform the scheduled work, the shut-off will be re-scheduled to Monday, August 20, 2018 at 9:00 AM**

The following locations will be affected:  

  • Linden  Street (#55 to #79)


Shut-off scheduled for Friday, August 17, 2018 at 11:00 AM
**If the contractor is unable to perform the scheduled work, the shut-off will be re-scheduled to Monday, August 20, 2018 at 11:00 AM**

The following locations will be affected: 

  • Linden  Street (#90 to #130)
  • Blake Street (#23 to #29)
  • Cypress Street (end to end) ?

If you have any additional questions or would like more information about this project, please feel free to stop by the Engineering Division at DPW. Residents may also call the Engineering Division at 
(781) 455-7550 and ask for David Kelly, Steve Nadeau or Tom Ryder.