Construction Schedule...anticipated, as of April 16, 2015

April 21-22           Clearing of brush along trail by contractor

April 23-24           Installation of erosion controls

April 27 - May 12  Removal of iron rails

May 13 - May 29  Removal of wooden ties

Some form of barrier will be installed just prior to reaching the Charles River, and just prior to reaching the High Rock bridge to show the ending points of the 1.7 mile pedestrian path. 

The surface will be back-bladed for informal use until the Town is able to complete the procurement process for the next stage of construction, which will include a stone dust surface, safety fencing, and improvements at the road crossings.